Lancang River dredging project is resumed

01/Apr/2020
From March 1st, the construction of the fourth channel of the Lancang River 244 boundary marker (China-Lao-Myanmar boundary) to Lincang Port-the underwater blasting of the Reef in Nanbang River and the waterway dredging of the Ganlan Dam  have been fully resumed. 146 engineering technicians and laborers carried out strict epidemic prevention inspections, and confirmed that there were no abnormalities before entering the site.It was used silt curtains and excavators. Since the project started in March 2019, the accumulated investment has reached 910 million yuan, and the cumulative investment since this year is 30 million yuan.