The River Dredging Project of Tuohe Depression Passed the acceptance of the contract project completion

29/Jan/2021

On January 18th, the Suzhou Municipal Water Conservancy Key Project Construction Administration hosted a meeting on the completion and acceptance of the river channel dredging contract project in the Tuohe Depression (Yongqiao District) of the Huaihongxin River System in Anhui Province.

The acceptance team listened to the reports of the project participating units on the project construction, checked the completion and quality of the project on site, and checked the acceptance data collation. After discussion, the acceptance team agreed that the project had completed all construction content as agreed in the contract and met the design requirements, and agreed that the project passed the contract completion acceptance.

The estimated total investment of the project is 43,219,800 yuan, and the length of the river dredging is 26.796km. After the completion of the project, it has effectively improved the irrigation and drainage functions of the Tuohe River Yongqiao section, improved the regional water environment, protected water resources, and had significant comprehensive benefits.It was used a large amount of silt curtains and dredgers were working for disposing the silt.


<< Back