Shenzhen Port Tonggu waterway dredging was staged completion
30/Nov/2019
Shenzhen Port Tonggu waterwat and the Western Port Public waterway 2019 maintenance dredging project was finished the staged completion.
According to reports, the construction is the maintenance dredging project of Shenzhen Port Tonggu waterway and the public channel of the western port area. The main construction contents include: First, they need dredge the existing channel back silt, and connect the Tonggu waterway and the western port area public channel. The southern section (about 3 kilometers) is dredged to -17.5 meters, and the northern section of the public waterway of the western port area (about 6 kilometers) is dredged to -14.5 meters. The construction period of this part was three months; the second was the maintenance dredging by using silt curtains and dredger after the completion of dredging, we need dredge once every three months (including one month of construction period) to ensure that the navigation channel meets the design requirements.